One-year free renewal
In order to cater to the demand of our customers, we will gather the newest resources through a variety of ways and update our SDM_2002001050 certification training: SDM Certification - NI regularly, then our operation system will automatically send the latest and the most useful SDM_2002001050 study guide to your e-mail during the whole year after purchase. We ensure you that our latest exam study guide will provide you the key points and the latest question types you need for the SDM_2002001050 exam files, and with these useful study materials, only practice 20 to 30 hours, you can surely pass the IT exam and gain the IT certification.
24/7 after sale service
Twenty four hours a day, seven days a week after sales service is one of the shining points of our company, the staffs who are responsible for after-sales service of SDM_2002001050 certification training: SDM Certification - NI in our company are always in good faith, patient and professional attitude to provide service for our customers. We are so proud that we have a lot of regular customers in many countries now, and there is no one but praises our after-sales service about SDM_2002001050 training materials. We keep the principle of "Customer is always right", and we will spare no effort to cater to the demand of our customers. So after buying our SDM Certification - NI exam study guide, if you have any questions please contact us at any time, we are waiting for answering your questions and solving your problems in twenty four hours a day, seven days a week.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
It is universally acknowledged that the IT certification is of great importance for IT workers, with the IT certification the workers can get their desired job easier and get promoted faster. However, passing the SDM_2002001050 exam is the only way for anyone to get the IT certification, which is a big challenge for many people. Fortunately our company aim to help those who want to pass exam with minimum effort. It is a great idea for you to choose our SDM_2002001050 certification training: SDM Certification - NI as your learning helper. We will try genuinely and sincerely to meet all the requirements of our customers.
Fair and reasonable price
Even though our SDM_2002001050 certification training: SDM Certification - NI are the best study materials in the IT field, we still keep our price of the exam study guide as the most favorable one in the market, just because we are devoted to letting as many people as possible to have access to these useful resources. What's more, we will provide discount for our customers in many important festivals. Owing to its superior quality and the reasonable price, our SDM Certification - NI exam study guide files have met with warm reception and quick sale in many countries. If you should become one of the beneficiaries of our IT SDM_2002001050 practice test in the near future, we would look forward to your favorable comments to us, and please feel free to recommend our products to your friends and colleagues.
Nokia SDM_2002001050 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| SDM Concepts & Framework | 25% | - Service Delivery Lifecycle - ITIL/COBIT Alignment - Nokia SDM Model & Principles |
| Service Operations & Governance | 30% | - Escalation & Stakeholder Communication - Service Monitoring & Reporting - Incident, Problem & Change Management |
| Service Design & Planning | 25% | - Customer Requirements & Expectations - Risk Assessment & Dependency Management - SLA, KPI & Service Catalog |
| Continuous Improvement | 20% | - Optimization & Improvement Initiatives - Customer Satisfaction & Service Reviews - Performance Analysis |
Nokia SDM Certification - NI Sample Questions:
1. Which main steps are required to set up an effective Change Management Process in a project?
A) - The change mgmt process is discussed and approved by NSN NI PjM team.
-The PM talks about the change management process with all relevant stakeholders internally in NSN.
-Follow-up mechanisms agreed like risk/operational reserves, EAC maintenance process, IPM CR set-up.
B) - The change mgmt process is discussed and approved by NSN NI PjM team.
-The change mgmt process is documented and communicated internally in NSN.
-
Follow-up mechanisms defined and agreed like risk/operational reserves, EAC maintenance process, IPM CR set-up.
C) - The change mgmt process is discussed and approved by customer/subcontractor/NSN NI PjM team.
-The change management process is documented and communicated to customer/subcontractor/internally in NSN.
-
Follow-up mechanisms defined and agreed like risk/operational reserves, EAC maintenance process, IPM CR set-up.
D) - The change mgmt process is discussed and approved by customer/subcontractor/NSN NI PjM team.
-The PM talks about the change management process with all relevant stakeholders internally in NSN and on the customer/subcontractor side.
-
Follow-up mechanisms agreed like risk/operational reserves, EAC maintenance process, IPM CR set-up.
2. Bulk orders from the customer to NSN are problematic for NSN because ...
A) ... the customer acceptance process cannot be easily broken down to site level which leads to delays in invoicing.
B) ... for the NSN logistics organization bulk ordering means that less customer POs need to be administrated which leads to underutilization of Logistics Coordinators.
C) ... it results in the fact that the customer has to accept too much scope at one time which can cause resource bottlenecks on the customer as well as on the NSN side.
D) ... for the NSN logistics organization bulk ordering means that more customer POs need to be administrated which leads to increased administrational effort.
3. An accuracy KPI has dropped significantly compared to previous periods. After some initial checks it turns out that the data is correct. What is the right way to proceed?
A) Organize a meeting with NPO in order to make a action plan to improve.
B) Organize a meeting with key team members in order to identify root causes and make an action plan to improve.
C) Communicate the deviation to the project stakeholders
D) Inform the CT head on the next CT meeting.
4. The customer has an urgent request for network tuning in a specific area due to significant cases of call drop, with the promise of increasing business opportunity in another area which is mainly in the hand of the other supplier (competitor), what's the correct way to answer this request ?
A) Iassure the customer that NSN is going to solve the problem by our professional network planning and optimization service, but in order to obtain all required resources and tools, it's necessary to have a purchase order to start the activities.
B) I will escalate this customer request to the Customer Team and ask to approve the related risk order.
C) This additional service improves the partnership between NSN and customer along with the high probability to increase the business and NSN footprint. Therefore I will act to complete this additional service as soon as possible without PO.
D) It's a major network problem for which NSN could get the blamE.therefore I will act to complete this additional service as soon as possible without hassling the customer with any administration.
5. What are the main responsibilities of the Cost & Progress Manager (EVM)?
A) That invoices aretimely processed andto avoid delays to subcontractor payments.
B) Cost control and monitoring, doing regular reviews with the Project Manager.
C) To issue the Purchase Orders in atimely manner to subcontractors.
D) to prepare the Baseline independently and present to PM for approval prior to project start.
Solutions:
| Question # 1 Answer: C | Question # 2 Answer: A | Question # 3 Answer: B | Question # 4 Answer: A | Question # 5 Answer: B |