One-year free renewal
In order to cater to the demand of our customers, we will gather the newest resources through a variety of ways and update our C-TS422-2601 certification training: SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing regularly, then our operation system will automatically send the latest and the most useful C-TS422-2601 study guide to your e-mail during the whole year after purchase. We ensure you that our latest exam study guide will provide you the key points and the latest question types you need for the C-TS422-2601 exam files, and with these useful study materials, only practice 20 to 30 hours, you can surely pass the IT exam and gain the IT certification.
Fair and reasonable price
Even though our C-TS422-2601 certification training: SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing are the best study materials in the IT field, we still keep our price of the exam study guide as the most favorable one in the market, just because we are devoted to letting as many people as possible to have access to these useful resources. What's more, we will provide discount for our customers in many important festivals. Owing to its superior quality and the reasonable price, our SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing exam study guide files have met with warm reception and quick sale in many countries. If you should become one of the beneficiaries of our IT C-TS422-2601 practice test in the near future, we would look forward to your favorable comments to us, and please feel free to recommend our products to your friends and colleagues.
It is universally acknowledged that the IT certification is of great importance for IT workers, with the IT certification the workers can get their desired job easier and get promoted faster. However, passing the C-TS422-2601 exam is the only way for anyone to get the IT certification, which is a big challenge for many people. Fortunately our company aim to help those who want to pass exam with minimum effort. It is a great idea for you to choose our C-TS422-2601 certification training: SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing as your learning helper. We will try genuinely and sincerely to meet all the requirements of our customers.
24/7 after sale service
Twenty four hours a day, seven days a week after sales service is one of the shining points of our company, the staffs who are responsible for after-sales service of C-TS422-2601 certification training: SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing in our company are always in good faith, patient and professional attitude to provide service for our customers. We are so proud that we have a lot of regular customers in many countries now, and there is no one but praises our after-sales service about C-TS422-2601 training materials. We keep the principle of "Customer is always right", and we will spare no effort to cater to the demand of our customers. So after buying our SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing exam study guide, if you have any questions please contact us at any time, we are waiting for answering your questions and solving your problems in twenty four hours a day, seven days a week.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
SAP C-TS422-2601 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Topic 1: Integration with Supply Chain and Integration with Extended Warehouse Management | 5% | - Integration with Quality Management - Integration with Extended Warehouse Management (EWM) - Integration of Production Planning with SAP SCM (Supply Chain Management) |
| Topic 2: Configuration and Implementation | 10% | - Organizational Units - Master Data Configuration - Migration and Data Transfer - Business Scenarios and Scope Items |
| Topic 3: Reporting and Analytics | 10% | - SAP Analytics Cloud Integration - Key Performance Indicators (KPIs) - Production Planning Reports |
| Topic 4: Production Orders | 20% | - Material Staging and Component Scrap - Creation and Processing of Production Orders - Order Settlement and Costing - Order Confirmation and Final Confirmation - Order Release and Printing |
| Topic 5: Production Planning for Process Industry | 15% | - Process Industries Specific Settings - Process Orders - Master Recipes and Formula Management |
| Topic 6: Material Requirements Planning (MRP) | 20% | - MRP Runs and Evaluation - Planning Strategies (Make-to-Stock, Make-to-Order, etc.) - Exception Messages and Alert Monitor - MRP Configuration and Parameters |
| Topic 7: Plan to Produce (PP) Processes | 20% | - Rough-Cut Planning - Sales and Operations Planning (S&OP) - Demand Planning (DP) - Supply Planning / Long-term Planning |
SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Sample Questions:
Question 1
Which material master data can you copy when you use the Copy Material program (transaction MMCC, Material Master Copier) to create new materials?
There are 2 correct answers to this question.
A. Production version data
B. Storage location data
C. MRP area data
D. Warehouse number data
Question 2
In the context of the capacity scheduling table, how do you define a pacemaker work center?
A. By assigning it to the capacity scheduling table
B. By assigning it to the production version
C. By assigning it to the first operation of a routing
D. By assigning it to the bottleneck operation
Question 3
You are trying to create a production order NO valid production version can be selected.
What could be the reasons?
Note: There are 2 correct answers to this question.
A. The order lot size is NOT within the validity range of a production version.
B. All production versions for the material are locked.
C. NO production lines are assigned to the production versions.
D. NO bills of material (BOMs) are assigned to the production versions.
Question 4
You have maintained the parameters for simple discontinuation in the material master of a component.
Which business process will be affected if the available stock is zero the discontinuation date is in the past?
A. Kanban
B. Material requirements planning
C. Production order release
D. Back flushing
Question 5
What could be the reason for multiple commitments where several operations have the same scheduled dates on a work center after dispatching?
Note: There are 2 correct answers to this question.
A. The work center has several individual capacities.
B. Alternative work centers are fully occupied.
C. The Change Planning Direction indicator is set in the strategy profile.
D. The Finite Scheduling indicator is NOT set in the strategy profile.
Solutions:
| Question 1 Answer: B,D | Question 2 Answer: B | Question 3 Answer: A,B | Question 4 Answer: B | Question 5 Answer: A,D |