SAP C-TFIN22-64 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Cost Object Controlling | 15% | - Order controlling and period-end closing - Product cost collectors - Work in process and variance calculation |
| Profitability Analysis | 5% | - Basic concepts and characteristics - Actual data transfer and reporting |
| Product Cost Planning | 20% | - Cost components, overhead calculation - Marking and releasing standard costs - Cost estimate with/without quantity structure |
| Internal Order Accounting | 15% | - Order types and master data - Availability control and status management - Planning, budgeting and settlement |
| Organizational Concepts and Master Data | 15% | - Controlling organizational structure - Internal orders and business processes - Cost elements, cost centers, profit centers |
| Cost Center Accounting | 20% | - Period-end closing activities - Actual cost postings and allocations - Planning and budget management |
| Profit Center Accounting | 10% | - Actual postings and period-end closing - Integration with New General Ledger - Master data and assignments |
SAP Certified Application Associate - Management Accounting (CO) with SAP ERP 6.0 EHP4 Essentials: What Candidates Ask
- Cost Center Accounting (20%)
- Internal Order Accounting (15%)
- Product Cost Planning (20%)
SAP Certified Application Associate - Management Accounting (CO) with SAP ERP 6.0 EHP4 Sample Questions:
Which of the following do you define in a library of the Report Painter?
- A. Characteristics and key figures.
- B. Predefined columns and rows.
- C. Formats and format figures.
- D. Report groups and reports.
Correct Answer: A 🗳️
For what purpose can you use a statistical internal order? Note: There are 2 correct answers to this question.
- A. Overhead surcharges.
- B. Settlement.
- C. Cost planning.
- D. Budget and availability control.
Correct Answer: C,D 🗳️
How can you achieve periodic controlling when a lot size based production scenario is used by logistics? Note: There are 2 correct answers to this question.
- A. Use an internal order in addition to the production order.
- B. Use a product cost collector in addition to the production order.
- C. Adjust the default rule in the default values for the production order type.
- D. Adjust the costing type of the plan costing variant.
Correct Answer: B,C 🗳️
To which organizational level do you have to assign the valuation area to create material costings?
- A. Company code
- B. Plant
- C. Business area
- D. Controlling area
Correct Answer: B 🗳️
Which of the following views and results do profit center accounting reports in New GL provide? Note: There are 3 correct answers to this question.
- A. Fixed and variable cost portions
- B. Balance sheet statement
- C. Variance categories of production
- D. Cost of goods sold
- E. Return on investment
Correct Answer: B,D,E 🗳️